Fairport Forward 2022 Capital Improvement Project Timeline

December 10, 2019

Capital Project and Capital Reserve Vote on 2019 Fairport Forward project (Phase I)

December 2019 - June 2021

Planning, design, bidding and approval process on Phase I

June 2021

Construction begins on Phase I of multi-phase Fairport Forward project

June 2021 - August 2022

Phase I construction continues at all FCSD buildings

April 26, 2022

Meeting with teams from LaBella Associates, Campus Construction and Dixon Schwabl + CO to discuss Phase II

April 2022 - July 2022

Development of scope of Phase II

August 2, 2022

Presentation of potential scope of Phase II project to Fairport Board of Education

August 2022

Meetings with partners and workshops with Board of Education to refine scope of Phase II

September 6, 2022

Students return for 2022-2023 school year to facilities updated by Phase I construction, Phase I construction continues

September 12, 2022

Review design and timeline of Phase II project at Board of Education workshop

September 20, 2022

Review final design and timeline of Phase II project at public Board of Education Business Meeting

September 23, 2022

Community and staff ThoughtExchange surveys launched to collect questions and comments on FCSD's facilities planning.

September 28, 2022

First staff-only presentations on Fairport Forward 2022

September - October, 2022

Multiple staff and community presentations on the scope of Fairport Forward 2022

October - November, 2022

Staff and community presentations on Fairport Forward 2022 continue

November 15, 2022

Superintendent and Asst. Superintendent for Business present Fairport Forward to Board of Education and field any additional Board questions